Specify separate first-article evidence for wire-EDM titanium dimensions, roughness and any surface-layer requirement on the drawing.

Table of Contents

Agree how each important titanium surface will be accepted before placing an order for wire electrical discharge machined (wire-EDM) parts. Dimensions and roughness address separate requirements. If the drawing also specifies a surface-layer condition, agree what evidence will verify that condition on the finished feature.

Does the wire-cut surface remain in the finished part?

Mark the face, slot wall or other feature on the controlled drawing. Identify whether the surface remains as cut or undergoes further finishing. Locate inspection on the stage that the drawing regulates and state who approves changes. In research on additively manufactured Ti-6Al-4V, investigators evaluated roughness and the recast layer separately after wire-EDM finishing. The study illustrates the distinction between measured properties on its specimens. Use the part's own specification to decide which properties need evidence. Original wire-EDM surface study

What should the first-article evidence cover?

RequirementEvidence to agree before the orderWho resolves a gap
Finished geometryFeature ID, drawing revision and results linked to the finished partBuyer design authority and supplier quality
Surface finishSpecified parameter, measurement location and agreed reporting basisSupplier quality and the drawing owner
Surface-layer condition, where specifiedAgreed inspection or examination report tied to the feature or an approved representative specimenDesign and quality authorities
Further processing or route changeRevision and confirmation of where the required evidence still appliesProcess approver and the buyer's technical owner

Consider a slot wall with a conforming dimension report and an accepted roughness reading. If the drawing also calls for a surface-layer examination, the reviewer can record geometry and finish as checked while keeping the surface-layer requirement open. If the proposed examination uses a separate specimen, ask the drawing owner to approve how it represents the material condition, process route and location before relying on the result.

Concept illustration of geometry, surface finish and specified surface-layer evidence feeding first-article review.
Concept illustration of first-article evidence categories. The cards represent review topics, not actual inspection results or acceptance criteria.

What if the drawing never defined a surface-layer criterion?

Raise the question before award when the service condition makes it material to the design owner. Ask whether the drawing needs an applicable requirement, where it applies and what record is expected. Write the revision into the order and first-article plan. CNC titanium parts buying guide

Frequently asked questions

Does every wire-EDM surface need sectioning?

Inspection depends on the approved drawing and acceptance plan. Ask the design owner what evidence the feature needs.

Does a roughness result verify the recast layer?

Use roughness for the specified surface profile. A separate surface-layer requirement needs the evidence agreed for that property.

When can a witness specimen be used?

When the buyer has accepted how it represents the finished feature and relevant processing conditions.

What if a later operation removes the wire-cut surface?

Specify the condition required at the finished feature and agree which evidence must follow the later operation.

What if a supplier changes its manufacturing route?

Have the authorized parties determine which prior evidence is still applicable and which checks must be repeated.

What should a first-article report identify?

Tie the result to the part or approved specimen, marked feature, controlled revision and relevant inspection stage.

Request a drawing and inspection review

Send HELE TITANIUM the material condition, released drawing, marked feature and any surface or post-processing requirement. Identify the first-article evidence that needs agreement. Review custom titanium machining · Send the drawing basis

Prepare a technical enquiry

Share the product form, grade or standard, dimensions, quantity and inspection requirements.

Ask a technical question →

References

Portrait of Bobby Fu

Project contact

Bobby Fu

Co-Founder · Senior Project Manager

Bobby Fu is a co-founder and senior project manager at HELE Titanium, with a background in international product development and manufacturing. His project work covers titanium materials, titanium anodes, and PEM water electrolysis systems. He works with industrial buyers and production teams to clarify material specifications, equipment interfaces, and inspection requirements before orders are placed.

View Bobby’s Profile
WhatsApp