Can You Accept a PEM Electrolyzer Delivery Before Installation?
Identify which PEM electrolyzer packages can be received at each location, which exceptions stay open, and what records are needed for installation release and SAT.
Table of Contents
When the purchase order provides for separate milestones, the receiving team can sign for the equipment it has identified and inspected at each agreed delivery location. Record the packages received, what could be checked and any exceptions. Release to installation and site acceptance testing require their own evidence and approval. A signature for goods received covers the scope stated on that record.
Record what arrived at each location
Use one controlled equipment list for the project site and any contracted warehouse. At each location, match the packing list to the crate or package identifiers and the equipment tags or serial numbers available for inspection. Record the destination, receiving date, packaging condition and the name of the receiving organization. If an identifier is enclosed in sealed packaging, record which outer identifier was verified and who will witness the remaining check.
If a crate is missing, damaged or sent to the wrong location, identify the specific item and record the condition before moving it. Use the project's approved options for provisional receipt, inspection hold or other disposition. Assign an owner and a closeout condition to each exception. A consolidated record should tell the installation team which items are available, which remain in custody and which cannot yet be released.
Keep receipt, installation release and SAT separate
| Milestone | Record to request | Approval to confirm |
|---|---|---|
| Goods received | Packing-list reconciliation by location, visible condition, identity checks and open exceptions | Who can sign receipt, and which items or checks the signature covers |
| Release for installation | Transfer record, equipment identity and condition, applicable custody records, open holds and confirmation of readiness for the item | Who closes the holds and who authorizes handover to the installation team |
| Site acceptance testing (SAT) | Approved protocol, evidence for the installed configuration and agreed duty, deviations and disposition | Who witnesses the relevant tests and who signs the specific acceptance milestone |
Agree the custody record before delivery. It should identify where the equipment may be held, which version of the supplier's instructions applies, what records the custodian must keep and how a planned storage extension or move is approved. If the site becomes unavailable or the equipment condition changes, ask the designated equipment authority for a written review before releasing the affected items. Use the PEM stack buying guide for the stack-specific documents and the PEM electrolyzer buying guide for system and site responsibilities.

Concept diagram showing project-site and contracted-warehouse receipts feeding a goods-received record, followed by separate installation release and site acceptance testing. Conceptual delivery records only, not a photograph of Rijeka or a HELE project. Goods receipt, release for installation and site acceptance testing require separate evidence and approvals under the agreed project requirements.
What the Rijeka evidence shows
In its 17 November 2026 preliminary assessment for Croatia, the European Commission describes a goods acceptance record for a 10.35 MW PEM electrolyzer package at INA's Rijeka refinery. Under Milestone 51, the evidence list records that INA and its contractor signed on 26 August 2026. The analysis says the equipment went to storage at the refinery site, with the electrolyzer stacks held at a nearby contracted facility. European Commission preliminary assessment, Milestone 51, Evidence No. 3
INA's project page describes electrolyzer installation separately and gives expected timing for first hydrogen production. The evidence reviewed here establishes the recorded delivery and storage arrangement. The project documents for installation, installed testing and operational release represent separate milestones. INA Rijeka project page
For a PEM project delivery review, send the planned shipment list by location, the expected site-ready date and the acceptance milestones. Include the proposed equipment scope, whether the stack and system travel separately, and any custody or inspection conditions to be agreed.
Frequently asked questions
Can one receiving record cover packages delivered to different locations?
Use the contract-approved form and identify each location, shipment and verified package. Attach the local receiving records and list any discrepancies by item so the status stays clear after consolidation.
How should we document a serial number that cannot be seen through the packaging?
Record the outer package reference and the scope of the identity check completed at receipt. Agree when the internal identifier will be verified and who will witness that check.
Who approves a storage extension if installation is delayed?
Follow the agreed authority and governing equipment instructions. Give the reviewer the equipment identity, location, current custody record and proposed change so any conditions or additional checks can be documented.
What if a warehouse accepts a crate with visible damage?
Record the condition, package identity, date and supporting evidence. Use the agreed disposition process to determine whether the receipt needs an exception and whether release for installation stays on hold.
What should the installation team receive when a stack moves to the site?
Provide the transfer record, reconciled equipment identification, available condition and custody evidence, and the disposition of any open exceptions. Confirm the receiving team can identify the items cleared for handover.
Which record shows SAT was completed or the warranty period started?
Use the signed site acceptance record and agreed protocol to establish SAT status. Ask the contract owner to identify the record and milestone that govern the warranty period for the specific order.